Tyson Park Redevelopment
Tyson Park updates are coming soon! After securing funding and navigating land use requirements, park improvements will begin in 2026. Join a virtual neighborhood meeting to see the proposed final park design and updated project timeline. After the meeting, the design and presentation will be uploaded to this page.
Tyson Park Neighborhood Meeting
RANGE
Free
Join this virtual meeting to see the proposed final park design and updated project timeline for the Tyson Park redevelopment project. There will be closed captions available in multiple languages, including Spanish.
Project Timeline
- Feb.-March 2024: Community members provided input on future updates to Tyson Park through surveys, meetings, and focus groups.
- April 2024-Sept. 2025: Willamalane sought additional funding and worked with the City of Springfield on land use review and updated permitting requirements. New emergency access routes were added to the design, extending the original project timeline.
- Fall 2025-Winter 2026: The project is in the permitting process.
- December 16, 2025: A virtual neighborhood meeting will cover the updated project timeline and proposed final park design. Closed captions are available in multiple languages, including Spanish. Join the meeting.
- Spring/Summer 2026: Construction will take place at Tyson Park.
- Fall 2026: Estimated completion for Tyson Park redevelopment work.
The project timeline may shift as needed.
Contact
If you have questions about the project, please email simon.daws@willamalane.org.